INSTALLATION:
H.T. SWITCHGEAR
& METERING PANEL:
All standard checks of the equipment before installation
shall be done by the Contractor and unit shall be installed and tested as per
direction of the manufacturer and Consulting Engineer. Required finishing work
shall be done by the Contractor and hooking up the unit with the system shall
also be within this contract. Consumable materials required for complete
installation of the equipment including cables compound, boxes etc. shall be
supplied by the Contractor. After complete installation be unit shall be tested
by the Contractor upto the satisfaction of the Consultant and the
Engineer-in-charge.
All accessories shall be installed as per
direction of the Manufacturer and the Consultants. If the equipment is damaged
during handling and installation. The Contractor must repair the damage or
replace the damaged parts at his own cost,
TRANSFORMER:
The Transformer equipments
should be checked
before installation by
the Contractor and installed and tested as per direction of
the Manufacturer and Consulting
Engineers and Engineer-in-charge / Consultant.
Required finishing work shall be done by the
Contractor and hooking up the transformer with the system shall also be within
this contract. Consumable materials required for complete installation
including cable compound boxes etc. shall be supplied by the Contractor and the
rate quoted shall be inclusive of all incidental expenses. Care should be taken
during carrying the transformer and its
related parts. if there is any damage during handling and installation the
Contractor will be liable to replace the damaged parts at his own expenses.
After complete installation the transformer must be tested and commissioning as
per direction of the Engineer-in-charge / Consultant, Manufacturer and
Consultant.
L.T. SWITCHGEAR:
All L.T. Gear equipment must be installed on
proper foundation. All consumables required for the complete work shall be
supplied by the Contractor. The work shall be complete with all internal
electrical connections. After complete installation of the panel the Contractor
should test the complete L.T. Gear equipment as per manufacturer specification
and direction for full satisfaction of the Consultant and Engineer-in-charge.
CAPACITOR:
The item includes supervision of installation
of capacitor on prepared foundation. The foundation is to be prepared by Contractor as per direction of the
Engineer-in-charge / Consultant. All consumables required to install the
equipment shall be supplied by the Contractor. After completion of the
installation the Contractor should test the equipment in presence of Consultant
to his satisfaction.
EARTHING
SYSTEM:
The work under this item shall consist of
supply and installation of earth electrode
with copper lead, earthing inspection pit and connecting to the
specified terminal according to the drawing, specification and direction of the
Engineer-in-charge / Consultant. The whole electrical system including light,
fan, regulator sockets sub-station and metal parts incorporated with building
electrification shall be earthed.
The earth resistance of the electrodes system
shall be to the satisfaction of the local supply authority and shall not exceed
in one ohms.
Materials
:
Earth
Electrode :
The earth Electrode in a 1 and 1/2” dia, G.I.
pipe with 3/16th inch. dia drilled holes.
The G.I. pipe shall be similar to the
specification.
The pipe earth electrode shall be sunk and
buried below ground level upto its full length or as advise by the
Engineer-in-charge / Consultant. The earth lead and be connected to the earth
electrode by brass/G.I. clamp. After
making connection the clamp shall be covered with bitumen poured hot and with
jute cloths.
Earth lead
:
Earth lead shall consist of two numbers, 2
SWG high conductive electrolytic bare copper wire meeting the requirement of
B.S.S. 6360 : 1969 and/or it’s equivalent.
All earth lead shall follow the shortest and
most direct route to the earth electrode avoiding sharp bend and from
inspection pit to the entry at the building shall be enclosed in 1” dia G.I.
pipe. The earth lead shall be connected to test earth electrodes by means of
lugs, bolts, nuts and double washers to fixed as to make permanent and positive
connections both electrically and mechanically. The joints shall be covered
with PVC compound without disrupting the continuity.
Earth Inspection Pit :
Inspection pit shall have to be constructed
over earth electrode to inspect and test the connection terminals. bricks used
shall be of Ist class and only approved quality cement shall be used, Jhama
brick khoa for R.C.C. cover shall be 3/4th inch down graded and washed, cleaned
before casting. 3/8th inch dia M.S. Rods @ 4” c/c with two 1/2” dia M.S.
Hook shall be provided in the cover
slab.
Installation :
Electrode
:
The pipe earth electrode shall be sunk and
buried below ground level upto its full length or as devised by the
Engineer-in-charge / Consultant. The earth leads shall be connected to the
earth electrode by silicon aluminum bronze body clamp and phosphor bronze
screws. After making connection the clamp shall be covered with bitumen poured
hot and with jute cloth.
Lead :All earth
lead shall follow the shortest an most direct route to the earth electrode
avoiding sharp bend and from inspection pit to the earth electrode avoiding
sharp bend and from inspection pit to the entry at the building shall be enclosed
in 1” dia water grade PVC pipe. The earth lead shall be connected test earth
electrodes by means of lugs, bolts, nuts and double washers of failed as to
make permanent and positive connections both electrically and mechanically. The
joints shall be covered with PVC compound without disrupting the continuity.
Pit :
Ist class brick made inspection pit and RCC
cover with Sub-Station & Diesel Generator Set Set hook shall be built on earth electrode as
described here above at the location shown on the drawings the electrode shall
be within 10’-0 from the building.
Maximum Earth Loop
Resistance :
The maximum earth loop resistance any point
in the installation including earth lead to the earth electrodes shall not
exceed the resistance specified in the schedule or that indicated by the
Consultant. The contractor must ensure that the leads are efficiently bonded to
all metal work other than the current carrying parts. So that the above
resistance level is not exceeded. It will be the duty of the contractor to provide
earth tester, test the installation in presence of the authorized
representative of the authority and submit earth test report to the authority
for approval.
Method of Measurement :
Measurement shall be per set of earthing system installed.
GENERATOR
:
ITEM :
DIESEL ENGINE Driven A.C. generator set
having a prime power output as per schedule (continuous rating) standard
voltage 230/415 volts, 3-phase, 50Hz, 4-wire at 1500 rpm under condition of
normal temperatures and pressures. The manufacturer must have ISO9001.
GENERAL
DESCRIPTION:
The engine and alternator assembly shall be
directly flanged coupled, the alternator being driven by a flexible coupling
connecting engine fly wheel to alternator rotor.
The unit should be mounted together with
cooling radiator on a fabricated, heavy steel frame of all welded construction
designed to accurately align and support the assembly. The base frame is to be
predrilled to allow for ant vibration mounts and is to be provided with special
Sub-Station & Diesel Generator Set Setting arrangement for case of handling
and safety purposes.
There must be arrangement for manual/
automatic battery electric start being operated from the main control panel
which shall also include all monitoring and protection devices covering the
mechanical and electrical systems.
DETAILED
SPECIFICATION:
Diesel engine driven generating set having a
continuous rated output at 0.8 Power factor at 415/230 Volts, 3-phase, 4-wire,
50Hz at 1500 RPM under conditions of normal temperatures and pressures with 10%
overload for one hour at conditions specified under B.S. 5514, DIN6271, ISO
3046/1.
ENGINE:
The engine shall be of 6 cylinders, 4 stroke,
Air to Air after cooled, turbocharged, pressure lubricated, direct injection,
water cooled, industrial type Diesel engine developing the rated bhp at 1500
RPM, at NTP conditions.
The engine shall be complete with close
control governing to BS 5514, 1979 Class A1 Fuel Injection equipment with :
a) Fuel
oil filters
b) Lubricating
oil filters
c) Air
cleaners/filters
d) Fuel
solenoid energized to run,
e) Lubricating
oil pressure pump,
f) Water
circulating pump,
g) Battery
charging generator,
h) Precision
mechanical governor,
i) Starter
motor,
j)
Fuel solenoid
k) Thermostatically
controlled by pass system
ENGINE STARTING:
The engine shall be fitted with manual
automatic electric starting by means of a starter motor arranged to engage with
the fly wheel.
ENGINE COOLING:
The diesel engine shall be cooled via a
tropical air blast heavy duty radiator
with engine driven pusher type
fan, complete with water circulating pump, radiator guard, thermostat and by
pass system.
BATTERIES:
The unit shall be supplied with a set of suitably rated heavy duty
12/24 volt industrial type lead acid batteries (dry charged). A mains operated
battery charger should be mounted in control cubicle.A set of starter cables
and connections would be supplied loose.
LUBRICATING
SYSTEM:
Wet sump force feed lubrication system by
gear driven oil pump incorporating replaceable oil filters.
EXHAUST
SYSTEM :
The engine
shall be supplied with: Acoustic type silencers, flexible bellows
sections and rigid exhaust pipe of suitable length, suitable for use with Vee
form engine, supplied loose for site erection. The complete exhaust system
shall be designed to prevent any de-rate of the engine due to excessive back
pressure. All exhaust components are to be finished with heat resistant paint.
ALTERNATOR
:
Brushless Salient pole rotating field,
self-exciting, self-regulating, single bearing construction with integral
automatic voltage regulator providing voltage control to within +/- 2% of
nominal range, no load to full load and at all power factors between unity and
0.8 lagging and with a maximum 5% prime mover speed variation.
Class H insulating on both rotor and stator
windings and with enclosures to IP21 of BS 4999 Part 20, IEC & DIN
standards. The alternator meets the requirement of BS 5000 and radio
suppression to BS 800 & VDE class G&N.
ANTI-VIBRATION
MOUNTINGS:
A set of anti-vibration mounts and spring
isolator would be supplied loose for positioning beneath bed frame when the
side is delivered to site. These have their own in - built leveling device and friction pad, therefore fixing to the
floor is not necessary.
FUEL
SYSTEM:
The unit shall be supplied with a base
mounted fuel tank in corporate in the base frame of the unit providing
sufficient fuel for 8 hours continuous full load operation, the base shall be pressure tested prior to
assembly and will incorporation dial type
content/gauge, filler cap, vent
pipe, drain cock and all necessary fuel connections. All pipe terminations
shall be completed during works assembly. The system shall include arrangement
for low and high level alarm system of fuel. An additional daily fuel tank
(self Standing) of 1500 liter capacity with automatic supply type including
level switch & pump.
FUEL
TRANSFER:
A set of rotary type hand pump would be
supplied with 3 meters of flexible pipe, suitable for manual fuel transfer to
the daily service fuel tank.
COUPLING:
The alternator casing would be flange mounted
to the engine flywheel housing and the rotor shaft, coupled to the engine
flywheel through a flexible element to minimise torsional vibration throughout
the operating range.
BASE
FRAME:
The engine and alternator would be mounted on
a fabricated steel type base frame of welded construction adequately designed
to resist bending and torsional forces. The base frame shall accurately align
and support the assembly and shall provide Sub-Station & Diesel Generator
Set Setting points and location points for securing to the foundation.
SWITCHGEAR:
Switchgear and instrumentation shall be
mounted in totally enclosed, stove enameled sheet steel, set mounted control
panel fixed to the saddle frame of the alternator by means of rubber
anti-vibration mounts. The panel shall have provision for BBT connection. The control panel would have access to all
internal components and include the following:
1- OFF/MANUAL/AUTO
selector switch.
1- Frequency
Meter.
1- Volt
meter (0-500V) with selector switch (six positions)
3- Ammeters
(0-1000A) with selector switch.
1- 1000A
TP circuit breaker with adjustable thermal and adjustable magnetic trips.
1- Battery
charger indicator with ammeter.
1- Key
start switch
1- Hour
run recorder
1- Set
of relays and timers
1- Set
of cartridge type fuse
1- Set
of output terminals
1- Set of indicator lamps for fault indication of Low Oil
pressure, High Engine Temperature Gauge, over speed, Overload and reverse Power
relay, over crank.
1- Fault protection reset switch and 1- buzzer to draw
attention.
The Control Panel would be complete with all
internal wiring cables and accessories necessary for satisfactory operation and
maintenance. The control system should be manually reset once the fault is
rectified. All the failure circuits must incorporate a “Press to Test” facility
which when operated will remove the fault and shut the generating plant down.
Really a great post.I liked it and i will share it with others too.HT and LT Works in Tamil Nadu
ReplyDeleteHi,,,
ReplyDeleteVery informative blog this is !
But you must aware that Every Business industry needs a good optimization of electricity for the growth and development. Contact to Electrical Panel Manufacturers and Run your business without any hassle.
Transfo Tech Engineering are expert in manufacturing Electrical HT/LT Panels, Transformers and other electrical appliances..
ReplyDeleteThanks for sharing this very informative blog with us. I read your blog and find out that this is very useful and informative for those people who really need to know about it.
ReplyDeleteElectrical Panel Manufacturers
Main LT Panel Manufacturers
DG Synchronization Panel Manufacturers
Panel Manufacturers
LT Distribution Panel Manufacturers