2.11.1     General
                2.11.1.1 Every installation shall, on completion and before being energized, be inspected and tested. The methods of test shall be such that no danger to persons or property or damage to equipment occurs even if the circuit tested is defective.
                2.11.1.2 Periodic inspection and testing shall be carried out in order to maintain the installation in a sound condition after putting it into  service. Where an addition is to be made to the fixed wiring of an existing  installation, the latter shall be examined for compliance with the recommendations of the Code.
                2.11.1.3 The individual equipment and  materials which form part of the installation shall generally conform to the relevant Bangladesh Standard (BDS) wherever applicable. If there is no relevant Bangladesh standard specification for any item, these shall be approved by the appropriate authority.
2.11.2     Insulation Tests
                2.11.2.1 Insulation resistance test shall be made on all electrical equipment, using a self-contained instrument such as the direct indicating  ohm-meter  of the generator type. d.c. potential shall be used in these tests and shall be as follows:
                        Circuits under 230 volts                                                             500 volts
                        Circuits between 230 volts to 400 volts                                   1000 volts
                2.11.2.2 The minimum acceptable insulation resistance value is 5 mega ohms. Before  making connections at the ends of each cable run, the  insulation resistance measurement test of each cable shall be made. Each conductor of a multi-core cable shall be tested individually to all  other conductors of the   group and also to earth. If insulation resistance test readings are found to be less than the specified minimum in any conductor, the entire cable shall be replaced.
                2.11.2.3 All transformers, switchgears etc. shall be subject to an insulation resistance  measurement test to ground after installation but before any wiring is connected. Insulation tests shall be made between open contacts of circuit breakers, switches etc. and between each phase and earth.
2.11.3     Earth Resistance Test
                2.11.3.1 Earth resistance tests shall be made on the system, separating and reconnecting each earth  connection.
                2.11.3.2 The electrical resistance of the earth continuity conductor together with the resistance of the earthing lead measured from the connection with the earth electrode to any other position in the completed installation shall not exceed 1 ohm.
                2.11.3.3 Where  more than one earthing sets are installed, the earth resistance between two sets shall be measured by means of resistance bridge instrument. The earth resistance between two sets shall not exceed 1 ohm.
2.11.4     Operating Tests
                Current load measurement shall be made on equipment and on all power and lighting feeders. The current reading shall be taken in each phase wire and in each neutral wire while the circuit or equipment is operating under actual load conditions. Clip-on ammeters may be used to take current  readings. All light fittings shall be tested electrically and mechanically to check whether they comply with the standard specifications. Fluorescent light fittings shall be tested so that when functioning no flickering or choke singing is felt.
2.11.5     Inspection of the Installation
                On completion of wiring a general inspection shall be carried out by competent personnel in order to verify that the provisions of this Code and that of the Electricity Act of Bangladesh have been complied with. A certificate may be issued on satisfactory completion of the work in a format as shown in Appendix C. Items to be inspected are detailed in the following sections.
                2.11.5.1 Substation Installations : In substation installations, it shall be checked whether:
                -       The installation has been carried out in accordance with the approved drawings;
                -       Phase to phase and phase to earth clearances are provided as required;
                -       All equipment are efficiently earthed and properly connected to the required number of earth electrodes;
                -       The required ground clearance to live terminals is provided;
                -       Suitable fencing is provided with gate with lockable arrangements;
                -       The required number of caution boards, fire fighting equipment, operating rods, rubber mats, etc., are kept in the substation;
                -       In case of indoor substation sufficient ventilation and draining arrangements are made;
                -       All cable trenches are provided with noninflammable covers;
                -       Free accessibility is provided for all equipment for normal operation;
                -       All name plates are fixed and the  equipment are fully painted;
                -       All construction materials and temporary connections are removed;
                -       Oil level , bus bar tightness, transformer tap position, etc. are in order;
                -       Earth pipe troughs and cover slabs are provided for earth electrodes/earth pits  and the neutral and LA earth pits are  marked for easy identification;
                -       Earth  electrodes are of GI pipes or CI pipes or copper plates. For earth connections, brass bolts and nuts with lead washers are provided in the pipes/plates;
                -       Earth pipe troughs and oil sumps/pits are free from rubbish, dirt and stone jelly and the earth connections are visible and easily accessible;
                -       HT and LT panels and switchgears are all vermin and damp-proof and all unused openings or holes are blocked properly;
                -       The earth bus bars have tight connections and corrosion free  joint surfaces;
                -       Control switch fuses are provided at an accessible height from ground;
                -       Adequate headroom is available in the transformer room for easy topping-up of oil, maintenance, etc.;
                -       Safety devices, horizontal and vertical barriers, bus bar covers/shrouds, automatic safety shutters/door interlock, handle interlock  etc. are safe and in reliable operation in all  panels and cubicles;
                -       Clearances in the front, rear and sides of the main HT and LT and subswitch boards are adequate;
                -       The switches operate freely; the 3 blades make contact at the same time, the arcing horns contact in advance; and the handles are provided with locking arrangements,
                -       Insulators are free from cracks, and are clean;
                -       In transformers, there is no oil leak;
                -       Connections to bushing in transformers are light and maintain good contact;
                -       Bushings are free from cracks and are clean;
                -       Accessories of transformers like breathers, vent pipe, buchholz relay, etc. are in order;
                -       Connections to gas relay in transformers are in order;
                -       In transformers, oil and winding temperature are set for specific requirements  to pump out;
                -       In case of cable cellars, adequate arrangements exist to pump off water  that has entered due to seepage or other reasons; and
                -       All incoming and outgoing circuits of HT and LT panels are clearly and indelibly labeled for identifications.
                2.11.5.2 Medium Voltage Installation: In medium voltage installations, it shall be checked whether:
                -       All blocking materials that are used for safe transportation in switchgears, contactors, relays, etc. are removed;
                -       All connections to the earthing system are feasible  for periodical inspection;
                -       Sharp cable bends are avoided and cables are taken in a smooth manner in the trenches or alongside the walls and ceilings using suitable support clamps at regular intervals;
                -       Suitable linked switch or circuit breaker or lockable push button is provided near the motors/apparatus for controlling supply to the motor/apparatus in an easily accessible location;
                -       Two separate and distinct earth connections are provided for the motor apparatus;
                -       Control switch fuse is provided at an accessible height from ground for controlling supply to overhead travelling crane, hoists, overhead bus bar trunking;
                -       The metal rails on which the crane travels are electrically continuous and earthed and bonding of rails and earthing at both ends are done;
                -       Four-core cables are used  for overhead travelling crane and portable equipment, the fourth core being used for earthing, and separate supply for lighting circuit is taken;
                -       If flexible metallic hose is used for wiring to motors and other equipment, the  wiring is enclosed  to the full lengths, and the hose secured properly by approved means;
                -       The cables are not taken through areas where they are likely to be damaged or chemically affected;
                -       The screens and armours of the cables are earthed properly;
                -       The belts of belt driven equipment are properly guarded;
                -       Adequate precautions are taken to ensure that no live parts are so exposed as to cause danger;
                -       Ammeters and voltmeters are tested; and
                -       The relays are inspected visually by moving covers for deposits of dusts or other foreign matter.
                2.11.5.3 Overhead Lines : For overhead lines, it shall be checked whether:
                -       All conductors and apparatus including live parts thereof are inaccessible;
                -       The types and size of supports are suitable for the overhead lines/conductors used and are in accordance with approved drawing and standards;
                -       Clearances from ground  level to the lowest conductor of overhead lines, sag conditions, etc. are in accordance with the relevant standard;
                -       Where overhead lines cross the roads or cross each other or are in proximity with one another, suitable guarding is provided at road crossings and also to protect against possibility of the lines coming in contact with one another;
                -       Every guard wire is properly earthed;
                -       The type,  size and suitability of the guarding arrangement provided is adequate;
                -       Stays are provided suitably on the overhead lines as required and are efficiently earthed or provided with suitable stay insulators of suitable voltages;
                -       Anticlimbing devices and Danger Board/Caution Board Notices are provided on all HT supports;
                -       Clearances along the route are checked and all obstructions such as trees/branches and shrubs are cleared on the route  to the required distance on either side;
                -       Clearance between the live conductor and the earthed metal parts are adequate; and
                -       For the service connections tapped off from the overhead lines, cutouts of adequate capacity are provided.
                2.11.5.4  Lighting Circuits : The lighting circuits shall be checked to see whether:
                -       Wooden boxes and panels are avoided in factories for mounting the lighting boards, switch controls, etc.;
                -       Neutral links are provided in double pole switch fuses which are used for lighting control, and no fuse is provided in the neutral;
                -       The plug points in the lighting circuit are all  3-pin  type, the third pin being suitably earthed;
                -       Tamper proof interlocked switch socket and plug are used for locations easily accessible;
                -       Lighting wiring  in factory area is enclosed in conduit and the conduit is properly earthed, or alternatively, armoured cable wiring is used;
                -       A separate earth wire is run in the lighting installation to provide earthing for plug points, fixtures and equipment;
                -       Proper  connectors and junction boxes are used wherever joints are in conductors or cross over of conductors takes place;
                -       Cartridge fuse units are fitted with cartridge fuses only;
                -       Clear and permanent identification marks are painted in all distribution  boards, switchboards, sub-main boards and switches as necessary;
                -       The polarity has been checked and all fuses and single pole switches are connected on the phase conductor only and wiring is correctly connected to socket outlets;
                -       Spare knockouts provided in distribution  boards and switch fuses are blocked;
                -       The ends of conduits enclosing the wiring leads are provided with ebonite or other suitable  bushes;
                -       The fittings  and fixtures used for outdoor use are all of weatherproof construction, and similarly, fixtures, fittings and switchgears used in the hazardous area are of flameproof  application;
                -       Proper  terminal connectors are used for termination of wires (conductors and earth leads) and all strands are inserted in the terminals;
                -       Flat ended screws are used for fixing conductor to the accessories;

-          Flat washers backed up by spring washers are used for making end connections.